PROJEK-PROJEK YANG TELAH DISIAPKAN TAHUN 2008
Bil. |
Tajuk |
Pelanggan |
Jumlah(RM) |
Tarikh |
|
Mula |
Siap |
||||
1 |
Design and Supervision of Electrical Works for BLT Project: Kompleks Logistik PDRM Pulau Pinang |
NRS Asso /PBLT |
180,000.00 |
10-Nov-06 |
Ongoing |
2 |
KHTP – Independent Power Utility. Suppy, Installation And Commissioning Of Electrical System And Cabling For KTPC Kulim Perdana Housing In Kulim Hi-Tech Park |
NUR |
285,760.00 |
02-Jan-08 |
15-Jul-08 |
3 |
Penyenggaraan Pencegahan Pencawang TNB Nibong Tebal |
TNB |
63,443.00 |
08-Jan-08 |
15-Apr-08 |
4 |
Design and Supervision of Mechanical & Electrical Works for PKENPs Project: Taman Sena Indah, Kangar Perlis |
NRS Asso /PKENPs |
50,000.00 |
11-Jan-08 |
Ongoing |
5 |
PBT – Penyenggaraan Lampu Jalan |
Intan Segmen/PBT Hi-Tech |
45,000.00 |
15-Jan-08 |
Ongoing |
6 |
Relay testing and calibration for UniKL Kulm |
UniKL |
3,300.00 |
20-Jan-08 |
20-Jan-08 |
7 |
MSVR – Merombak, Menyusun Semula Sesalur Atas Voltan Rendah Di Kg. Ee Guan, Serdang, Bandar Bahru, Kedah Darul Aman. |
Panama Elektrik/TNB |
18,868.46 |
21-Jan-08 |
Ongoing |
8 |
B/E Untuk Fasa 1 Cadangan Skim Perumahan Di Atas Lot 8,10, 11, 316, 344, 444, 445 dan sebahagian Lot 5 & 6, Mk. Sg. Ular, Daerah Kulim, Kedah Darul Aman |
Panama Elektrik/TNB |
17,630.00 |
21-Feb-08 |
16-Apr-08 |
9 |
Electrical Inspection Works |
IWK A Setar |
18,960.00 |
01-Mac-08 |
28-Feb-09 |
10 |
Cadangan Kerja-kerja Perkhidmatan Penyelenggaraan Infrastruktur Sistem Bekalan Elektrik Selama Dua (2) Tahun Di UiTM Kedah, Kampus Sg. Petani, Kedah Darul Aman. |
UiTM |
200,791.00 |
01-Mac-08 |
28-Feb-10 |
11 |
Electrical Inspection Works – Empangan Beris |
JPS Kedah |
19,800.00 |
01-Mac-08 |
Ongoing |
12 |
Supply, Delivery and Installation of newly 4 units OCEF relays at BN Shipyard, Lumut, Perak |
Boustead Naval Shipyard |
17,000.00 |
24-Mac-08 |
15-Apr-08 |
13 |
Penyenggaraan Pencegahan Pencawang TNB Pulau Pinang |
TNB |
120,000.00 |
01-Apr-08 |
31-Dis-09 |
14 |
Repair of oil leaks at neutral bushing, filtration and dehydration 1 unit 15MVA 33/11kV transformer no 1 and functional test for all protection circuit. |
Boustead Naval Shipyard |
22,500.00 |
19-Apr-08 |
20-Apr-08 |
15 |
Kerja-kerja Perkhidmatan Penyelenggaraan Infrastruktur Sistem Bekalan Elektrik Selama Dua (2) Tahun Di UiTM Perak, Kampus Seri Iskandar, Perak Darul Ridzuan. |
UiTM |
185,992.00 |
01-Mei-08 |
30-Apr-10 |
16 |
Replacement of Low Voltage Power Cables for location 17/18, 20, 21/22 and 37 Warehouse |
Boustead Naval Shipyard |
500,000.00 |
15-Mei-08 |
22-Okt-08 |
17 |
Electrical Inspection Works |
IWK Taiping |
6,720.00 |
01-Jun-08 |
31-Mei-10 |
18 |
Tx Oil Sample Analysis |
Boustead Naval Shipyard |
15,456.00 |
01-Jun-08 |
23-Jun-08 |
19 |
Maintenance and Servicing of 11kV and 415V Equipment Including Relay Recalibration |
Taigene Metal (M) Sdn Bhd |
4,500.00 |
01-Jul-08 |
13-Jul-08 |
20 |
Maintenance and Servicing of 11kV and 415V Equipment At MAXIS TOC, Seberang Jaya |
EPE Switchgear/ Maxis |
14,450.00 |
08-Jul-08 |
09-Jul-08 |
21 |
Kerja-kerja Pemeriksaan dan Membuat Ujian Tatahan Kepada Geganti Untuk Loji-loji dan Rumah Pam JBA Negeri Kedah |
JBA Negeri Kedah |
57,760.00 |
14-Jul-08 |
18-Ogos-08 |
22 |
Supervising Electrical Engineer’s Inspection Services, PenangPort Sdn Bhd |
NRS Asso /PPSB |
154,800.00 |
01-Ogos-08 |
31-Jul-11 |
23 |
KHTP – Independent Power Utility Project. 11kV Cable Replacement for CS6-CS7 Circuit in Kulim Hi-Tech Park |
NUR |
60,090.00 |
24-Ogos-08 |
18-Sept-08 |
24 |
End to end test & line stability for current differential relay 7SD (siemens) – fibre optics |
TopRank Corp |
5,000.00 |
04-Sept-08 |
05-Sept-08 |
25 |
Service Of Work For LV Electrical System Inspection And Rectification Works |
RapidKL |
52,500.00 |
14-Sept-08 |
10-Okt-08 |
26 |
Pre-Commissioning Testing at PPU Bukhari, Alor Setar, Kedah. |
MHM |
1,700.00 |
03-Nov-08 |
08-Nov-08 |
27 |
Testing (VLF Test) of 33/11KV Cable at PPU Bagan Datoh, Perak |
MHM |
4,000.00 |
07-Nov-08 |
07-Nov-08 |
28 |
11KV Switchgear Testing & Commisioning at PPU Jalan Perusahaan Perai, Pulau Pinang. |
MHM |
19,400.00 |
17-Nov-08 |
30-Nov-08 |
29 |
Commisioning test for line protection between PMU Alor Setar (GIS) and PPU Taman Nuri. |
Swiss Const. |
4,000.00 |
22-Nov-08 |
21-Nov-08 |
30 |
33KV Cable VLF Test Between PMU Alor Setar (GIS) and PPU Taman Nuri. |
Swiss Const. |
2,800.00 |
22-Nov-08 |
21-Nov-08 |
31 |
Electrical Inspection Works |
SEMASA/ KWSP |
7,200.00 |
01-Dis-08 |
31-Dis-09 |
32 |
Penyenggaraan Pencegahan Pencawang TNB Bukit Mertajam |
TNB |
360,000.00 |
01-Sept-08 |
Ongoing |
33 |
Oil Reclaimation for transformers in BN Shipyard |
BNS |
68,000.00 |
17-Nov-08 |
30-Nov-08 |
33 |
Menaiktaraf Papan Suis Utama 415V Bagi Meningkatkan Penggunaan Set Janakuasa Tunggusedia di Empangan Beris, Sik, Kedah Darul Aman |
JPS Kedah |
19,000.00 |
11-Okt-08 |
17-Dis-08 |
34 |
Electrical Inspection Works |
Kolej Komuniti Kepala Batas |
10,800.00 |
01-Nov-08 |
31-Dis-10 |